|
Under the Mining Act, the Department
sets the conditions and requirements governing
exploration work before the start of fieldwork.
The authorization to carry out work does
not release the titleholder from any other legal
obligation that may apply to the area.
The following terms and conditions must be met, namely:
- for the Norebec-Manitou reserve
- The titleholder shall ensure that all
parts, goods, machinery and other equipment
necessary to carry out mineral exploration
shall not be stored near lands currently
being rehabilitated or to be rehabilitated
in the future, nor stored in such a way
as to limit or restrict access to the reserve.
- The titleholder shall be responsible
for the compliance of sub-contractors with
the conditions and requirements governing
mineral exploration.
- for the Lacs Guillaume-Delisle and
à l’Eau Claire, Rivière
Témiscamie, Monts Otish and Monts Puvirnituq
reserves
- No camp may be set up within the boundaries
of land reserved to the State or within
any adjacent territory where staking is
not permitted.
- No work may be carried out in the Rivière
Témiscamie itself and within a strip
of land 100 metres wide on either side
of the river, with the exception of work
required to pump water. Thus, if the distance
between the drilling site and the water
intake is greater than 200 metres,
the titleholder may be authorized to pump
water from the Rivière Témiscamie,
provided authorization is granted by the
Department, a high-protection lining is
installed under the pump to prevent potential
spills of petroleum products, and finally,
environmental impact is minimized.
- To the north of 55th parallel,
all grid lines must be blazed ontrees. To
the south of 55th parallel,
cutting of trees which are less than 12
cm in diameter at chest height is prohibited
for grid line marking. All grid line marking
must result in cutting the smallest amount
of trees possible, and should be carried
out using tape or paint, especially in forested
areas of low soil coverage or on steep slopes.
If tree cutting becomes necessary, the cut
line must not exceed one metre wide.
- Outcrop stripping, trench digging, excavating,
drilling and tree cutting must be limited
to the minimum required to carry out the
exploration activity. Single area affected
by one or more of the above-mentioned
activities must be less than five hectares.
All activity areas must be located at least
25 metres from each other. Finally,
the total cleared area resulting from such
activities must not exceed 5% of the total
land area covered by adjacent claims held
by the same company. These cumulative restrictions;
apply to all cleared land at once or successively
over a period of six years from the date
on which the land has been reserved to the
State.
- Land accessibility is only possible by
air. If the construction of roads becomes
necessary within the area concerned, a written
authorization must be obtained following
a study conducted by the Department.
- During work performance, any tool, material,
machinery, equipment and other accessories
normally used may be stored on-site,
providing fragile environments and high
ecological value sites are avoided.
- On the work site, scrap and other waste
must be stored in accordance with the standards
set in the Environment Quality Act.
The waste must be stored, processed and
eliminated at an authorized site outside
the State reserved land.
- If drilling work must be carried out into
a watercourse or in its vicinity, all sediments,
mud and waste must be deposited at least
30 metres from its natural high-water
mark. Waste left on-site is
prohibited once the work has been completed.
- All excavated areas must be filled up
once the activities have been completed.
- All cleared land must be replanted using
seedlings of the same species. Two years
after, the holder of mining rights must
verify, if the vegetation has grown back
adequately.
- Any planned work into a watercourse, lake,
marsh, swamp, peat bog or pond must be authorized
by the Ministère du Développement
durable, de l’Environnement et des
Parcs. In addition, it is mandatory to comply
with the 20 metre buffer zone required
by the Politique de protection des rives
du littoral et des plaines inondables
(protection policy for lakeshores, riverbanks,
littoral zones and floodplains).
- The holder of mining rights must provide
the accommodation and transportation between
the nearest airport and the site while inspections
are being conducted by any ministry or agency’s
representative, including the Ministère
des Ressources naturelles et de la Faune,
the Ministère du Développement
durable, de l’Environnement et des
Parcs and a representative of the Council
of the Cree Nation of Mistissini for sites
located along the Rivière Témiscamie.
Three inspections are normally scheduled.
- The holder of mining rights will be responsible
for ensuring that all sub-contractors
comply with the conditions and requirements
governing the work execution.
Work assessment
The authorization to carry out mining exploration
work on land reserved to the State will be granted for a maximum
period of six years from the date on which the land is reserved
to the State.
Before the expiry of the six-year period, the Department
will perform an assessment of the land’s mineral potential.
Following this assessment, the Department will determine if the
land contains inferred mineral resources as defined by the Canadian
Institute of Mining, Metallurgy and Petroleum. If this is the
case, the holder of the mining rights will be authorized to continue
his development work and the land concerned will be excluded from
the land reserved to the State. On the contrary, where no mineral
potential has been identified, all claims will be abandoned by the
claim holder in accordance with the Mining Act, without
any compensation from the State.
To allow the assessment’s completion and
the determination of inferred mineral resources, the holder of the
mining rights must forward a detailed report to the Department
setting out the exploration work completed and the results obtained,
at least 60 days before the State’s prerogative to reserve
the land from mining activity expires. |